Hot competition for oil stakes
p. 10 · Read in the full issue
AS Papua New Guinea readies for its first commercial oil output this year, the heat is on for stakes in the company.
Prime Minister Rabbie Namaliu wants to increase government interest in the SUSI billion oil development project in a move he believes would strengthen “direct involvement of the people of Papua New Guinea” in it.
But only days after Namaliu was told that the news is a surprise to Pioneer Int Ltd, from whom the government is to buy 25 per cent of shares it holds in a principal Kutubu project partner, Pion eer said it was not prepared to part with any of its shares of the 40 per cent it holds in Oil Search. With a 7.8 per cent stake, it is an active participant.
Namaliu said his government took a decision to buy Pioneer’s stake because the Australian company wanted to divest itself of oil interests. Analysts and some partners in Kutubu were also surprised why the government did not wait till it finalised negotiations before announcing its plans. Some suggested that govern ment might be pressuring Pioneer after an impasse in share-sale talks.
The speculation was that the Namaliu government, which has 2.24 per cent in Kutubu, was capitalising on the project for political gains. A general election is scheduled for about May or June. An investment of this size in Kutubu in the Southern Highlands would be a sizeable slice of the country’s annual budget.
An estimate was that the government could pay SUS23.I million for only 10 per cent of Pioneer’s holding in Oil Search. The share price stood at around USS 7 cents in December but if the sale was to go ahead the government may have to pay around US77 cents a share for it to be viable for Pioneer.
Namaliu said government investment in Pioneer would ensure Oil Search remained an independent PNG-based oil company. “It is my government’s hope
that in due course, as the country’s capital markets develop, these shares wili be sold on for direct investment by the people of PNG.”
The government sees a need for ar independent, PNG-based commercial domestic company as the country moves towards producing its own oil. “It is therefore, important to use the current opportunity to secure an additional significant block of shares in Oil Search on behalf of the people of PNG.”
PNG nationals in 1990 bought 10 pei cent of Oil Search, whose major asset is a 7.8 per cent stake in PNG’s first commercial oil field, Kutubu.
Namaliu said he expects the govern ment’s amicable relationship with Pion eer to continue, with the sale of PNG’: crude oil production into Pioneer’;
Australian refinery.
Kutubu was due to come on stream around June but delays in constructior means it would not start until the thirc quarter of 1992. Construction was slowec because of massive preparation work The construction was nearly half done ir December with hopes that lagifu, Hedinia/Agogo oil fields will start tc generate the first oil in the third quarter Oil will be extracted from three fields established so far from a total of 30 wells 13 of which have been drilled. The othei 17 wells are yet to be drilled. A 171.5 km pipeline from the Gulf of Papua oil field; is being constructed.
An airstrip has been built in the highlands at Moro to allow for hercules aircraft to transport materials.
Mining analysts involved in Kutubi believe that the project developers coulc also soon negotiate for the neigbouring South East Gobe oil field to be incorpor ated into the Lake Kutubu venture Located to the far south east of Kutubu South East Gobe is only 15km from the production pipeline which has enormous capacity to also carry output from SE Gobe. C